amend section 616 - sprinkler system to read as follows: “section 616 ‑ sprinkler system 616.01 description. this work includes installin

Amend Section 616 - Sprinkler System to read as follows:
“SECTION 616 ‑ SPRINKLER SYSTEM
616.01 Description. This work includes installing a sprinkler systems
such as piping, sprinkler heads, valves, automatic controllers, remote
control valves, booster pumps, valve assembly units, power and control
wiring, pullboxes, and related equipment and materials at locations
shown in the contract or as specified by the Engineer.
616.02 Materials. Materials shall conform to the following:
Trench Backfill Material 703.21
Polyvinyl Chloride (PVC) Pipe 706.13
Dark Green Enamel Paint 708.03
Pullboxes 712.06(B)
Frames and Covers 712.07(A)
Sprinkler Heads 712.12
Valves 712.13
Pressure Regulators 712.14
Backflow Preventers 712.15
Precast Concrete Meter and Valve Boxes and Covers 712.23
Cables, Conductors and Wires for Irrigation System 712.34(C)
Automatic Controller 712.42(A)
Pump, Motor and Motor Controller 712.43
Springs for Sprinkler Risers 712.47
Electrical Appurtenances 712.48
Valve Boxes and Covers (Plastic and Concrete) 712.49
Switching Tensiometer 712.50
Rain Sensor Switch 712.52
Cullet Materials for Drainage System 717.04
Materials and equipment incorporated in the irrigation system shall be
new and shall be of recognized standard quality. The Engineer will
inspect and test the materials according to the contract.
Electrical equipment shall conform to the NEMA Standards. Electrical
work shall conform to the National Electrical Code (the Code), General
Order No. 6 of the Hawaii Public Utilities Agreement, local power
company rules, and local ordinances that may apply.
Sprinkler water lines under the roadway shall be PVC pipe, Schedule 80
with threaded connections.
Concrete for reaction blocks, pump foundations and jackets shall be
Class B conforming to Section 601 ‑ Structural Concrete.
Within 10 days following the award of contract, submit a list of the
irrigation equipment that the Contractor will use on the project. The
list shall be by name of manufacturer and catalog number. The list of
irrigation equipment shall include sprinkler heads, valves, irrigation
control equipment, booster pump units, and pump controls as required
for the irrigation system.
Materials will be subject to inspection by the Engineer. Failure of
the Engineer to note faulty material or workmanship during
construction will not relieve responsibility by the Contractor for
removing or replacing such materials and redoing the work at no cost
to the State.
616.03 Construction Requirements.
(A) Installation.
(1) General. The irrigation system shown in the contract is
diagrammatic only. Provide the pipe fittings or substitute other pipe
fittings necessary to complete the connections shown in the contract.
Alterations and changes in the layout may occur to conform to the
ground conditions and to obtain full and adequate coverage of water.
Do not change or alter the system as planned without prior acceptance
by the Engineer.
Ream the pipes after being cut and clean and free the pipes from dirt
or other foreign matter. Make the metal to metal screwed joints with
an accepted non‑soluble and nontoxic lubricant on the male thread
only.
Excavate the necessary trenches and other openings a minimum of 18
inches of depth or to the required depth shown in the contract.
Excavate the additional depth and width where required, to ease
valves, reaction blocks, concrete jackets, rock removal, connections
to other mains or to clear subsurface obstructions. Trenches shall be
of sufficient width to permit snaking of plastic pipe not connected by
rubber ring‑type fittings. The Contractor need not snake the pipe
connected with rubber ring‑type fittings.
Trenches for plastic pipe shall be smooth and free of jagged rubble or
sharp objects that will cause abrupt bending stresses and uneven
weight distribution during backfilling operations. Before backfilling
the pipe line trenches in an area that the Contractor will water,:
(a) pressure test that unit of the irrigation system and
(b) modify the sprinkler locations if necessary to get complete and
uniform coverage or flow.
Supply line trenches located next to curbs, dikes, and paved shoulders
shall be at least four feet from said curbs, dikes, and paved
shoulders.
Install reaction blocks according to the manufacturer's instructions
and as specified by the Engineer. Furnish a copy of the manufacturer's
instructions to the Engineer before installing the pipes.
When installing supply lines through existing paved areas, replace the
subbase, base, and paving removed with material of equal quality.
Set the risers for sprinklers on slopes approximately perpendicular to
the plane of the slope or half‑way between perpendicular to slope and
vertical for best coverage. Install each series of sprinklers and
adjust and test operate the nozzles to establish the location on the
slope and proper angle of the risers.
If the location of a supply line interferes with the drilling of plant
holes, locate the plant holes to clear the supply lines. Do not
install supply lines through plant holes except in the installation of
emitters or bubble heads.
Install the vertical spring action check valves on the sprinkler
risers or swing joints shown in the contract or specified by the
Engineer.
Before the Contractor removes or disturbs markers showing the location
of existing cross‑over conduits, mark the conduit location on the
pavement.
Connect the underground metallic pipes, valves or fittings made of
dissimilar metals through a dielectric coupling or bushing. Separate
these pipes physically from other metal objects a minimum of one‑eight
inch. The Contractor may require non‑conducting spacers that will
insure physical separation of pipe from foreign objects as decided by
the Engineer.
Before any portion of the pipeline on the supply side of a control
valve is backfilled, expel the air from the line. Then turn the water
and maintain at full pressure for not less than 8 consecutive hours.
Also, before any portion of the pipeline on the discharge side of a
control valve is backfilled, do a similar test except the test shall
be for a duration of one hour. Repair leaks that develop in the
portion of the system installed by the Contractor and replace
defective materials at no cost to the State. Plug or cap the pipe
where the Contractor will install sprinklers while making this test.
Then check the entire system for uniform and complete coverage after
installing sprinklers.
After installing the pipe and testing the pipe properly according to
the contract, backfill and compact the trench in 6 inch layers
according to Section 206 ‑ Excavation and Backfill for Conduits and
Structures. Dispose of the remaining material.
In planting areas, the Contractor may compact the backfill material by
ponding or jetting with water until the backfill material, after
settlement, is level with the surrounding soil. Fill the pipeline with
water before compacting the backfill material.
Backfill the pipe trenches so that sharp objects will not damage the
pipe. Do not place rocks directly on the pipe.
When backfilled area has settled, refill and compact said area
including furnishing, applying, and compacting the fill material.
When meeting solid rock, excavate the rock:
(a) to a depth 6 inches below the invert grade and
(b) to a width four inches on each side of the pipe.
Backfill the space up to the invert with trench backfill material.
Compact the trench backfill material firmly.
Install the pressure regulators and backflow preventers according to
the Plumbing Code of the respective County.
(2) PVC Pipe. Join the plastic pipe and fittings by solvent cementing,
slip seat joints, or threaded joints. Cuts shall be square‑end and
clean. When clamping the pipe, protect the pipe from nicks and
scouring by wrapping in canvas, emery paper or other accepted
materials.
Install the plastic pipes and fittings according to the manufacturer's
instructions and procedures. Furnish a copy of the printed
instructions to the Engineer before installing the pipe. The
Contractor shall be responsible for making arrangements with the pipe
manufacturer for field assistance.
In making solvent cement joints, do not apply pressure until the
joints cure for an adequate time.
Screw the threaded joints and apply an accepted non‑hardening,
putty‑type joint compound. Avoid undue strain on plastic material. On
plastic to steel connections, make the steel connections first.
Tighten the threaded joints about one turn past hand‑tight with a
strap wrench.
Install the plastic pipes to allow for expansion and contraction as
recommended by the manufacturer's instructions and procedures.
(3) Valves and Valve Boxes. Construct the valve manifolds shown in the
contract.
If the contract shows multiple installations of valves in a large
single valve box, the Contractor may, at its option, install the valve
in individual valve boxes. Install the valves with a two inch
clearance from valve box walls.
Install the valve boxes with their tops one inch above the surface of
surrounding grade. In concrete walks or traffic islands, flush the top
of the valve boxes with the surrounding grade.
The Contractor may substitute plastic valve boxes for portland cement
concrete valve boxes.
(4) Valve Keys. Furnish to the Engineer upon completion of the
project:
(a) two long shank keys or wrenches for flow adjustment of manual
control valves and
(b) two valve keys for four inch or larger gate valves.
(5) Electric Automatic Controllers. House each controller in a
pedestal type enclosure. Install the controller on a portland cement
concrete foundation or wall mounted shown in the contract. The
concrete for the foundation shall be Class B and shall conform to
Section 601 ‑ Structural Concrete. The Engineer will permit hand
mixing of foundation concrete.
Each controller shall have an individual neutral conductor to its
respective valves.
Submit a complete maintenance and operations manual for each type of
controller to the Engineer before the plant establishment period.
A complete schematic wiring diagram for each controller shall be a
part of the maintenance manual. The diagram shall show in detail the
circuits and parts. Also, submit one copy of said diagram in a heavy
plastic envelope and attached to the inner portion of each controller
cabinet door.
Electrical equipment requiring modifications to conform to the
contract shall have such modifications made at the factory before
shipment to the project.
(6) Valve Assembly Unit. The valve assembly unit shall be of the same
size as the pipeline that said unit serves.
(B) Water Service Connection. Install the water service connection
according to the requirements of the appropriate County Water Supply
or governing agency. Furnish and install the service lateral, service
connection, meter, meter box, shut‑off valve, valve box and
miscellaneous items necessary to complete the connection. This
includes excavation, backfilling and tapping into the water main.
(C) Relocation of Existing Sprinkler Lines. Reinstall the indicated
sprinkler lines at the new locations according to Subsection 616.03(A)
‑ Installation. If the Contractor cannot reuse the existing lines,
install new material.
The Contractor may use compression type fittings to connect new lines
to existing lines.
Furnish and install a valve box at each relocated valve or multiple
valve installations.
(D) Electric Service. The electric company will provide electric
services to the irrigation system from its facilities or existing
facilities shown in the contract. The electric services includes the
equipment and features shown in the contract. Apply to the electric
company for the required services under the applicable rate schedule.
The Engineer will pay such charges the electric company levies. The
Contractor shall pay energy charges up to the time of final acceptance
of the project.
(E) Field Test. Before the acceptance of the work, conduct the
following tests on the automatic sprinkler system circuits in the
presence of the Engineer:
(1) Test for continuity of each circuit.
(2) Test for grounds in each circuit.
(3) A megger test on each circuit between the circuit ground. The
insulation resistance shall not be less than the values specified in
Section 110‑20 of the Code.
(4) A functional test to show that the system functions as specified
or as intended herein.
Replace or repair faulty material or installation revealed by these
tests according to the contract. Repeat the same tests until no fault
appears.
(F) Sprinkler Heads. Install the sprinkler heads at the locations
shown in the contract or as modified and accepted by the Engineer.
The Contractor shall locate:
(1) lawn spray heads or lawn pop‑up spray heads four inches away from
curbs, sidewalks, and pavements;
(2) shrubbery spray heads 12 inches away from curbs, sidewalks and
pavement; and
(3) jet sprinkler heads or rotary pop‑up jet sprinkler heads five feet
away from curbs, sidewalks, edge of shoulder or pavement or
(4) as specified by the Engineer.
Install lawn pop‑up spray heads and rotary pop‑up jet sprinkler heads
on swing joints or flexible swing joints.
(G) Installation of Electrical Materials.
(1) Equipment List and Drawings. Within 30 days following the award of
the contract, submit for acceptance 6 copies of a list of materials
and equipment that the Contractor will incorporate in the work. The
list shall include the name of the manufacturer, data and catalog
number of equipment, detailed scale drawings and wiring diagrams of
the systems and proposed deviations from the contract. If required,
submit for acceptance samples of the materials that the Contractor
will use at no cost to the State.
(2) Excavation and Backfill. Excavation and backfill shall conform to
Section 206 ‑ Excavation and Backfill for Conduits and Structures.
(3) Concrete for Transformer and Equipment Cabinet Pads, Cabinet
Bases, and Conduit Encasement. Concrete for transformer and equipment
cabinet pads, cabinet bases, and conduit encasement shall be Class B.
They shall conform to Section 601 ‑ Structural Concrete. Reinforcing
steel shall conform to Section 602 ‑ Reinforcing Steel. Welded wire
fabric reinforcement shall conform to Subsection 709.01(C).
Forms shall be true to the lines and grades as accepted. Forms shall
be rigid. Brace the forms securely in place. Place the conduits and
anchor bolts in the proper position and to the proper height. Hold the
conduits and anchor bolts in place with a template until the concrete
sets. Allow the concrete pads to cure for 7 days and the concrete for
conduit encasement to cure for 72 hours.
Concrete pads shall be level and have a steel trowel finish. Notify
the electric company 24 hours before placement of concrete for
transformer pads or conduit encasement.
* (4) Circuits.
(a) Buried Conductors. The Contractor may bury or install circuits
operating at a nominal potential of 30 volts directly or in conduit.
Unreel direct burial wires and cables alongside the trench and place
carefully on the bottom of the trench. The Engineer will not permit
unreeling and pulling the cable into the trench from one end. Before
backfilling, verify that the cable is free of kinks and sharp bends.
The Engineer will permit splices only in electrical pullboxes marked
"Electric" or valve boxes housing electric control valves. Make the
splices to provide a watertight joint of dielectric value at least
equal to the conductor insulation.
Leave at least two feet of slack in each conductor at each splice and
at each remote control valve. Bundle directly buried wires with nylon
straps at five-foot intervals.
(b) Conductors in Conduits. Install circuits operating at a potential
above 30 volts nominal in conduit. Before installing the wire or cable
in conduit, pull a suitable wire brush, swab and mandrel through the
conduit to remove extraneous matter. Verify that the conduit system is
free of obstructions. Pull the cable directly into the conduit from
the shipping coil or reel before installation. Do not uncoil and lay
the cable on the ground. Make the pulls in one direction. Use only
lubricants recommended by the manufacturer of the wire or cable or
accepted by the Engineer. Do not leave the wires and cables under
tension nor tight against bushings or fittings. When using pulling
grips, remove the damaged ends when pulling the wire or cable. Do not
pull the cable with its end open. Maintain the seal.
Cables shall be continuous from pulling point to pulling point. The
Engineer will not permit splices elsewhere. Make splices and taps with
standard splicing kits of type recommended by the cable manufacturer.
Splices shall be waterproof and of dielectric value at least equal to
that of the insulation of the conductors joined.
(c) Conductors. Conductors shall be of the size shown in the contract
or larger as recommended by the manufacturer of the controllers
furnished for this project.
Tag each conductor in each pullbox and each conductor terminal at each
controller and remote control valve with a small permanent
identification tag or band. The tags or bands shall be embossed,
non‑ferrous metal, or rigid plastic. The embossed symbols shall
contrast with the background color. Identification on each tag or band
shall include the controller station, and number or letter designation
of the controller serving the remote control valve.
(d) Bonding and Grounding. Ground noncurrent‑carrying parts of the
electrical system, including metallic portions of conduit systems,
equipment and device enclosures, and equipment frames.
(e) Conduits. Metallic conduit shall be rigid zinc‑coated steel.
Non‑metallic conduit shall be PVC conduit or bituminous‑fiber duct
(BFD). Non‑metallic conduit encased in concrete shall be PVC Schedule
40, thin wall type for the BFD kinds. Non‑metallic conduit directly
buried shall be PVC Schedule 80, heavy wall type for the BFD kind.
Apply the conduit types shown in the contract.
Install the rigid metal conduit according to Article 346 of the Code.
Use white and tinted ready‑mix paint on the threads of joints. Repair
the zinc‑coated surfaces according to Subsection 501.03(G)(2) ‑
Repairing of Damaged Zinc‑Coated Surfaces.
Cut rigid PVC conduit with a hack‑saw. Square and trim the cut ends to
remove rough edges. Construction shall be of the solvent‑weld type.
Make the solvent‑weld joints according to the conduit manufacturer's
recommendations and as accepted by the Engineer. The Engineer will
permit preassemblying sections of conduits.
Cut the bituminous‑fiber lengths with tapering tools recommended by
the manufacturer. Couplings shall be of the same material as the
conduit that the couplings join.
Do not use such force as to damage the coupling. Install the ducts to
drain toward either one or both pullboxes or manhole.
Make directional changes in non‑metallic conduit runs with curved
equipment using accepted deflection couplings or with short lengths of
straight ducts and couplings. The deflection angle between two
adjacent lengths of duct shall not exceed 6O nor shall the bends give
a radius of less than 12 times the nominal size of the conduit unless
using factory‑made ells.
Use only hand shovels in compacting the concrete jacket unless the
Engineer authorizes other methods. Cure the concrete for at least 72
hours before permitting vehicular traffic to run over the concrete.
(5) Pullbox. Space the pullboxes shown in the contract or at a maximum
spacing of 250 feet. Install pullboxes with their tops one inch above
the surface of the surrounding grade. In concrete walks or traffic
islands, flush the top of the pullboxes with the surrounding grade.
(I) Water Service. Arrange with the appropriate County Water
Department for the water service. The Contractor shall pay for the
water and service charges during the period of use of the sprinkler
system. For water service from existing State water system, the
Contractor shall install a water meter to establish the Contractor's
prorate usage and cost.
(J) Acceptance. The Engineer will not accept the sprinkler system
until the end of the plant establishment period. The sprinkler system
shall be operating according to the contract for the section the
Engineer is accepting.
Operate the automatic type sprinkler system in the automatic mode for
at least three weeks before acceptance. Repair the breakdowns in the
system occurring during this period at no cost to the State.
(K) Workmanship. Install materials and equipment according to the
contract. Remove and replace material when specified in writing by the
Engineer at no cost to the State.
A licensed plumbing Contractor or an experienced journeyman plumber
shall do the irrigation pipe work. A Licensed Electrical Contractor or
an experienced journeyman electrician shall do the electrical work.
The contract defines plumbing and electrical work and the Contractor
shall conform to "Title 16, Chapter 80, Rules Relating to Electricians
and Plumbers, Chapter 448E, HRS", and "Chapter 448E, HRS, Electricians
and Plumbers".
Iinstall sprinkler systems and automatic sprinkler control systems
according to the contract.
616.04 Method of Measurement. The Engineer will not measure the
sprinkler system for payment.
(A) Irrigation system will be paid on a lump sum basis. Measurement
for payment will not apply.
(B) The Engineer will measure components of the system per each in
accordance with the contract documents.
616.05 Basis of Payment. The Engineer will pay for the accepted pay
items listed below at the contract price per pay unit as shown in the
proposal schedule. sprinkler system on a contract lump sum basis.
Payment will be full compensation for the work prescribed in this
section and the contract documents.
The Engineer will pay for the copper service laterals and copper
service connections under Section 624 - Water System.
The Contractor shall pay for the water used before the acceptance of
the project or until the termination of the maintenance period for the
plantings, whichever is later.
The price includes full compensation for furnishing and installing the
sprinkler system; excavating; backfilling; installing concrete and
reinforcing steel for reaction blocks, pipe sleeves in catch basins
and retaining walls; connecting to existing sprinkler systems;
installing pipe fittings, valve and pressure regulator boxes, service
connections; making the required tests; and furnishing labor,
materials, equipment, tools and incidentals necessary to complete the
work.
The unit price for sprinkler head includes the riser, swing joint,
fittings and other necessary items to connect to the lateral line.
The Engineer will pay for the accepted high voltage work above 30
volts on a contract lump sum basis. The price includes full
compensation for work done from the electric company's facilities up
to the controller(s) or the State distribution panel; hookup; and
furnishing labor, materials, equipment, tools, and incidentals
necessary to complete the work.
The Engineer will pay for the accepted low voltage work up to 30 volts
on a contract lump sum basis. The price includes full compensation for
work done from the sprinkler control valves to the controller(s) or
the State distribution panel; hookup; and furnishing labor, materials,
equipment, tools, and incidentals necessary to complete the work.
The Engineer will pay for each of the following pay items when
included in the proposal schedule:make payment under:
Pay Item Pay Unit
Permanent Irrigation System Lump Sum
Temporary Irrigation System Lump Sum
Components of the System Linear Foot, Each
Sprinkler System Lump Sum
High Voltage Work Lump Sum
Low Voltage Work Lump Sum
The Engineer will pay for:
(1) 80 percent of the contract bid price upon completion of the
system.
(2) 20 percent of the contract bid price upon completion of the plant
establishment period.
The Engineer will pay for the copper service laterals and copper
service connections under Section 624 - Water System.
The Contractor shall pay for the water used before the acceptance of
the project or until the termination of the maintenance period for the
plantings, whichever is later.”
END OF SECTION 616
==================
(Project No)
616-13a 1/10/05

  • THE ROLE OF GENE BANKS IN FINDING AND CONSERVING
  • RETTSMEDISINSK PROTOKOLL FOR UNDERSØKELSE AV PASIENT SOM ANGIR SEKSUELT
  • ADATBEJELENTÉS AZ ÉPÜLET ÉPÜLETRÉSZ UTÁNI ÉPÍTMÉNYADÓRÓL F Ő
  • MINISTERO DELL’ISTRUZIONE DELL’UNIVERSITÀ E DELLA RICERCA ISTITUTO D’ISTRUZIONE
  • LAMBETH AND SOUTHWARK COMMUNITY FOOT HEALTH SERVICES REFERRAL
  • SEMPRE MENO DIPENDENTI E SERVIZI PUBBLICI NELLA PUBBLICA AMMINISTRAZIONE
  • ADATLAP AZ ADATVÉDELMI NYILVÁNTARTÁSBA BEJELENTETT ADATKEZELÉSRŐL NYILVÁNTARTÁSI SZÁM 40933
  • DOM ZDRAVLJA BOLJEVAC BR5 1539118 OD 01VI 2018GOD NA
  • SUCCESS MEASURES RESPONSE TO THE GOVERNMENT GREEN PAPER ON
  • ADÓABC HASZNÁLATI ÚTMUTATÓ BEVEZETŐ A KUTATÁSUNK SORÁN KIDOLGOZOTT ADÓABC
  • GRUPO 70 ESTÁGIO SUPERVISIONADO III – MODALIDADE REMOTA (20XX)
  • RD INSTRUCTION 1970I TABLE OF CONTENTS PART 1970 –
  • ADÓELŐLEGNYILATKOZAT 2010 ÉVBEN AZ ADÓELŐLEG MEGHATÁROZÁSA SORÁN FIGYELEMBE VEHETŐ
  • 6 DECRETO NÚMERO 3615 DE 2005 HOJA NO CONTINUACIÓN
  • CURS DE FORMARE A ABILITĂȚILOR DE MEDIERE FORMULAR DATE
  • EDSS 545 A AND B SECONDARY SCIENCE METHODS (30
  • ADATLAP AZ EGYSÉGES MUNKAÜGYI NYILVÁNTARTÁSBA TÖRTÉNŐ BEJELENTÉSEKHEZ I MUNKAADÓRA
  • DIPLOMADO EN INTERPRETACIÓN Y ARGUMENTACIÓN JURÍDICA DIRECTORES ACADÉMICOS DR
  • OCFS0014 (REV 72005) NEW YORK STATE OFFICE OF CHILDREN
  • ADATLAP KÜLFÖLDI SZOLGÁLATRA TÖRTÉNŐ JELENTKEZÉSHEZ NÉV RENDFOKOZAT A MEGPÁLYÁZOTT
  • D EPARTAMENTO DE DESARROLLO HUMANO DE LA OEA PROGRAMA
  • TYPES OF NARRATIVE PATTERNS LINEAR JOURNEY OF CENTRAL CHARACTER
  • TITULO LA ARCHIVÍSTICA Y LOS PRODUCTOS INFORMÁTICOS CATÁLOGO
  • ADÁSVÉTELI SZERZŐDÉS HIRDETMÉNYI ÚTON TÖRTÉNŐ KÖZLÉSÉRE IRÁNYULÓ KÖZZÉTÉTELI KÉRELEM
  • PROSPECTUS FOR SHORTTERM CLIMATE SIMULATIONS USING THE CCSM PETER
  • ADATVÉDELMI TÁJÉKOZTATÓ BAKONYI ERŐMŰ ZÁRTKÖRŰEN MŰKÖDŐ RÉSZVÉNYTÁRSASÁG TÁVHŐ ÜGYFELEK
  • ADATVÉDELMI TÁJÉKOZTATÓ FILMJUS ADATVÉDELMI TÁJÉKOZTATÓ A FILMJUS EGYESÜLET
  • ADATKEZELÉSI TÁJÉKOZTATÓ WWWREFLEXSHOPHU BEVEZETÉS A YOCORE BT (4028 DEBRECEN
  • DET KONGELIGE HELSE OG OMSORGSDEPARTEMENT POSTBOKS 8011 DEP 0030
  • DEVOIR COMMUN DE SES 1ES1ES2 DURÉE QUATRE HEURES