pipeline name [xx” production pipeline] ======================================= applicant [holder of the pwa] =========================
PIPELINE NAME [XX” Production Pipeline]
=======================================
APPLICANT [Holder of the PWA]
=============================
PROJECT NAME [Field Name] Development Project
=============================================
Reference Drawing
=================
Col 1
Col 2
Col 3
Col 4
Col 5
Col 6
Col 7
Col 8
Col 9
Col 10
Col 11
Col 12
Pipeline No.
Ident No.
From
To
Description of Component Parts of the Pipeline
Length (m)
Ext. Dia
(mm)
Int.
Dia
(mm)
w.t
(mm)
Type
of
Insulation/coating
MAOP (Barg)
Products
to be
conveyed
PLXXXX
Start point of pipeline with Geographical co-ords
End point of pipeline with Geographical co-ords
XX” Production Pipeline
(Oil/Gas etc.)
1
Each different point of the pipeline to be noted with start and end
sections
2
3
Table 1: [XX” Production Pipeline]
If it is a production pipeline it should start at the Well or the
Manifold and then go to the FPSO/Platform as the fluids will be coming
from the reservoir to the FPSO/Platform.